Scope: Structural, Mechanical and Piping
Location: Dalby, Surat Basin QLD
Value: $10.5 Million Incl.
IN BRIEF
Contracted by CPECC WDS Joint Venture (JV) in 2015 to complete the installation of civil, structural, mechanical, piping, electrical and instrumentation scope of works for the three compressor expansion of the Arrow Energy Daandine Central Gas Processing Facility (CGPF) near Dalby in Queensland.
Pipemech worked with CPECC WDS JV in the lead up to site mobilisation to finalise the scope of work and installation methodology which included a complex, time constrained plant shut down to tie in the three new compressor installations.
CUSTOMER BENEFITS
Upon contract award Pipemech quickly mobilised its experienced management, supervisory and labour teams to undertake a rapid ramp up to full production and efficiency at the CGPF site initially managing and driving the completion of the civil works in order to allow SMP and E&I works to commence.
Pipemech further assisted Clough Amec JV (CAJV) with the inspection and reporting of progress on the overseas fabrication packages.
Pipemech were able to develop and successfully implement a methodology that took account of the restricted site working area and weight of the new compressors using a heavy lift ‘lock and lift’ system.
As part of the SMP and associated shut down planning Pipemech assessed and provided options for the most cost and schedule effective means of undertaking hydro testing of the works to CAJV and Arrow Energy.
Pipemech successfully completed the SMP elements of scope required on time during the CGPF shut down, allowing Arrow Energy to reintroduce gas to the plant as planned with all works being performed in compliance with the Arrow Energy isolation permitting requirements. The scope of work completed during the shutdown included;
Following the completion of the CGPF shutdown, Pipemech’s team moved into the completion and pre-commissioning phase of works at the CGPF which was heavily reliant on the Pipemech in-house developed innovative weld traceability software package.
Pipemech have also been able to assist CPECC WDS JV with completion of discrete scope on the Production Facilities / Gathering elements of the project in addition to undertaking the procurement of materials, plant and suppliers to ensure a successful project outcome for Arrow Energy.
TECHNICAL FEATURES
Scope: Electrical and Instrumentation
Location: Dalby, Surat Basin QLD
Value: $10.5 Million Incl.
IN BRIEF
Pipemech’s experienced E&I team complimented by their E&I QA/QC team executed an Arrow Energy’s planned shutdown of the CGPF for the expansion and tie in of three x Ariel JGC/6 reciprocating compressors, one x TEG Generation package, TEG contactor tower, glycol filter, fuel gas and buffer vessel, inlet coalescer, oil filter, inlet separation boot and production facility flow lines. Following the shutdown, the team completed installation of the E&I Scope of Work for the new compressor packages including hazardous area auditing, UCP and MCC installations.
CUSTOMER BENEFITS
Pipemech’s E&I leadership team including experienced Electrical Engineers, worked closely with the client to create work methodologies for the safe execution and tie in to existing electrical infrastructure given the operating plant conditions.
Pipemech’s E&I QA/QC team conducted all MCC testing, hazardous area inspections, instrument inspections, cable tests, earth grid tests and following all testing, Pipemech’s E&I Engineers produced all as build documentation to complete the handover dossiers.
E&I TECHNICAL FEATURES
E&I QA/QC FEATURES
E&I ENGINEERING FEATURES
Scope: Inlet Seperator
Location: Dalby, Surat Basin QLD
Value: $0.5 Million Incl
IN BRIEF
Based on the Pipemech teams' knowledge and experience in pipeline installation and deep excavations in confined/restricted areas on operational sites, CPECC WDS JV requested Pipemech’s assistance with the installation methodology, risk management, estimating and installation supervision of the Daandine Central Gas Processing Facility (CGPF) gas inlet separator pipe.
Pipemech developed and assessed seven separate options and estimated two of these prior to finalising the agreement of EPC Clough Amec JV (CAJV) and Arrow Energy for the selected installation methodology.
CUSTOMER BENEFITS
Pipemech’s experience and input into this project allowed for the safe, on time and under budget installation of this complex element of work within a live gas facility.
Consideration to the proximity of existing live gas infrastructure, as close as 1.4m to the proposed new pipe, underground electrical cables at the edge of the excavation, and installation of the inlet pipe under the CGPF Flare line, was given to the safe methodologies and risk management.
Procedures employed prior to and during installation by Pipemech.
Pipemech proposed the installation of the pipe within a 4.7m deep trench, straight walled on one side to avoid impacting existing infrastructure and one bench on the opposite side to allow for personnel access to the side of the trench. This trench arrangement combined with the use of a large trench box at the gathering tie in under the CGPF Flare line, accurate excavation and flowable bedding and padding allowed for the elimination of the entry of personnel into the trench until within safe depths.
Vacuum excavation and use of zero slew excavators was employed to minimise the risk of live infrastructure strikes during the excavation of the trench.
Using a 50t crane and 11m spreader bar Pipemech was able to ensure the pipe was lifted in an approved manner and installed at exactly the correct position for the gathering and CGPF tie ins.
TECHNICAL FEATURES
Scope: Pre Commissioning / Commissioning
Location: Dalby, Surat Basin QLD
Value: $10.5 Million Incl.
IN BRIEF
Pipemech’s pre-commissioning team were tasked with delivering each system ready for start-up once mechanical completion was accepted by the client.
The scope included electrical energisation of new and existing equipment; instrumentation loop checks; PLCDCS integration; motor bumping; alignments, and first fills of all equipment/vessels; oil flushing, and nitrogen/helium leak testing.
Commissioning/Start-up assistance to the Arrow Operations team was also part of the scope to bring the plant back online upon completion of the shutdown, and also assist with start-up of the new TEG, and three compressor packages in addition too, 22 wells in the gathering network.
CUSTOMER BENEFITS
Pipemech’s pre-commissioning teams’ prior experience in compression and plant equipment was a valuable asset to the client project team, by way of population of the completions management system to ensure all testing of PLC logic, instrumentation and equipment was completed to ensure a seamless transition into commissioning.
The Pipemech pre-commissioning team also completed pre-commissioning of Arrows gathering network of 22 well heads across three well pads, including providing assistance to the Arrow/Clough Amec Joint Venture operations to commission and start-up the well.
TECHNICAL FEATURES
Scope: Pre Commissioning / Commissioning
Location: Dalby, Surat Basin QLD
Value: $0.5 Million Incl.
IN BRIEF
Pipemech’s experienced Civil, SMP, E&I and Quality teams were tasked with the complete installation and pre-commissioning of 22 well head skids, six gas generators and three remote terminal unit MCC’s on three well pads for the expansion of the Arrow Energy Daandine Production Facilities.
The scope included civil works, mechanical skid installation, interconnecting pipework, electrical and instrumentation installation, pre-commissioning, vendor/commissioning support, and all associated completions and QA/QC.
CUSTOMER BENEFITS
Working closely with our client, Pipemech was able to safely complete the works, managing labour and supervision across multiple work fronts, including the Central Gas Processing Facility expansion and Production Facilities scope mitigating several scope increases and emergent works to maintain schedule for both discrete project elements.
Pipemech’s experienced team was able to provide a complete solution, encompassing all works, and associated support functions required to leave the well pads in a state fit for purpose ready for the introduction of hydrocarbons.
TECHNICAL FEATURES
Project: Matilda John Coal Seam Gas Field Compressor Station
Location: QGC Tenements, Central Fields, Surat Basin QLD
Value: $9.1 million
In Brief:
Commissioned by QGC in 2013 to carry out the complete structural, mechanical and piping installation of a 2 train Field Compressor Station in the Central Fields of the QGC tenements. The successful construction of this plant led to the award of three further FCS sites, two in the Central Field and one in the Northern Fields to date.
Customer Benefits:
Our company’s ability to mobilise highly skilled site management and supervisory teams experienced in a number of similar construction designs, combined with an extensive database of trade personnel, enabled a smooth construction process right from initiation through to the award of mechanical completion. We delivered to the client a product of the highest quality within schedule, enabling the client to meet critical commissioning deadlines for the Central Fields while maintaining ZERO Loss Time Injuries.
Pipemech’s commitment to maintaining flexibility with our clients contracting strategies meant that we were able to convert this contract from Lump Sum to Cost Reimbursable having already completed 90% of the scope. This conversion allowed for a 30% cost saving to the client on the original contract works value.
Pipemech’s extensive resources have allowed us to further supply ongoing labour support for the pre-commissioning and commissioning phases of this project outside the contract scope helping our client to achieve their critical deadlines.
Technical Features:
Project: Kate Coal Seam Gas Field Compressor Station
Location: QGC Tenements, Central Fields, Surat Basin QLD
Value: $7.5 million
In Brief:
On the successful completion of Matilda John Field Compressor Station, Pipemech was commissioned by QGC in 2013 to carry out the complete structural, mechanical and piping installation of the three 3 train Kate Field Compressor Station located in the Central Fields of the QGC tenements.
Customer Benefits:
Taking lessons learnt from the construction of the Matilda John Field Compressor Station, Pipemech was able to mobilise quickly and move a complete management team directly to Kate to carry out site establishment works.
Pipemech’s ability to mobilise highly skilled site management and supervisory teams experienced in a number of similar construction designs, combined with an extensive database of trade personnel, enabled us to build on the construction efficiencies using an experienced SMP team delivering a further 20% total cost saving on the Matilda John FCS price to the client.
Mechanical Completion for Pipemech’s scope is scheduled to be achieved in May 2014, two months ahead of the client schedule.
Technical Features:
Project: McNulty Coal Seam Gas Field Compressor Station
Location: QGC Tenements, Central Fields, Surat Basin QLD
Value: $7.5 million
In Brief:
On the successful completion of Matilda John Field Compressor Station, Pipemech was commissioned by QGC in 2013 to carry out the complete structural, mechanical and piping installation of the four train McNulty Field Compressor Station located in the Central Fields of the QGC tenements.
Customer Benefits:
Taking lessons learnt from the construction of the Matilda John and Kate Field Compressor Stations, Pipemech was able to mobilise quickly and move a complete management team directly to McNulty to carry out site establishment works.
Pipemech’s ability to mobilise highly skilled site management and supervisory teams experienced in a number of similar construction designs, combined with an extensive database of trade personnel, enabled us to build on the construction efficiencies using an experienced SMP team delivering a further 20% total cost saving on the Matilda John FCS price to the client.
Technical Features:
Project: Ross Coal Seam Gas Field Compressor Station
Location: QGC Tenements, Northern Fields, Surat Basin QLD
Value: $7.5 million
In Brief:
On the successful completion of Matilda John Field Compressor Station, Pipemech was commissioned by QGC in early 2014 to carry out the complete structural, mechanical and piping installation of the four train Ross Field Compressor Station located in the Northern Fields of the QGC tenements.
Customer Benefits:
Taking lessons learnt from the construction of the Matilda John, Kate and McNulty Field Compressor Stations, Pipemech was able to mobilise quickly and move a complete management team directly to Ross to carry out site establishment works.
With a steady man power ramp up in alignment with the progressing civil construction schedule, Pipemech have been able to build on the construction efficiencies using an experienced SMP team and ensuring only the highest quality of workmanship.
Technical Features:
Project: QLD Compressor Station Unit 4 Upgrade
Location: Charleville QLD
Value: $5.8 million
In Brief:
Commissioned by APA Group in 2013 to deliver a Scraper Station Unit Upgrade including Earthworks, Civil Works, Steelwork, Piping Demolition, Piping Installation, Electrical and Instrumentation Removal and Installation Works allowing for a bi-directional flow capacity.
Customer Benefits:
Under the capable direction of Pipemech’s Project Management team, trades and labour personnel worked diligently within a tight schedule to ensure APA Group’s Eastern Haul Project delivered a successful outcome within the planned duration of the shutdown. This project was conducted onsite some 95 km from Charleville amid extreme summer temperatures.
The company rolled out comprehensive safety management protocols and strategies to alleviate the risk of heat stress and fatigue, resulting in no recordable injuries during the project.
Integral to the seamless delivery of construction works during the shutdown, Pipemech ensured a transparent interface between its team and other stakeholders involved in the project. Pipemech’s electrical and instrumentation subcontractor was strategically scheduled with planned pipe fabrication, field weld placement and spool installation to minimise the time spent onsite during the shutdown.
The combination of Pipemech’s planning, systems and staff underpin its ability to deliver a successful outcome whilst maximising value for money for the client.
Technical Features:
Project: Supply, fabrication & installation of 40 gas compressions and associated infrastructure - 2006 to 2010
Location: Surat Basin, QLD
Value: $30 million
In Brief:
Commissioned by Queensland Gas Company (QGC) to undertake early field development works at the Berwyndale, Kenya and Codie Gasfields, located within the Surat Basin area of Queensland.
Contract works commenced in 2006 and continued until 2010 and comprised the supply, and fabrication of structural steelwork, pipe spooling, supply of miscellaneous items and the installation, testing and commissioning of Field Compressor Stations (FCS) and Central Processing Plants (CPP) external fabricators.
Customer Benefits:
Being contracted to supply, and fabricate the structural steel component from our Workshop in Brisbane, delivery was fast-tracked and coordinated with the site installation schedule. This offered the client a seamless, cost effective and time efficient transition from fabrication offsite to installation on-site.
This freed up the client’s procurement team from involvement and minimised the risk inherent in coordinating timeframes when dealing with external fabricators. The deployment of a professional management team, complemented by highly skilled trades personnel, and by offering direct interface between fabrication, and installation units. All projects were delivered on time and on budget.
Technical Features:
Scope of Works – on-site installation of structural steel, mechanical items and pipe work, and pipe spool fabrication
Locations -
Field Compressor Stations
Central Processing Plants
Brown field works:
Head Office
Unit 5 – 6 Enterprise DrivePhone: +61 7 5536 1180
Email:
info@pipemech.com.au